Fidelity Financial Corporate Hangar
Jacksonville, Florida
-
Standing Seam (SSR) Roof System
-
Panel Rib wall panels
-
Rigid Frame (clear span)primary framing
-
3,000 SF of office mezzanine
-
Framing, roof systems and wall systems complete in six weeks. |
|
Nichia Manufacturing Facility
Macon, Georgia
-
Standing Seam (SSR) Roof System
-
Panel Rib Walls
-
Continuous Beam primary framing
-
8.5" secondary.
-
400,000 SF manufacturing facility with maximum eave height of 75'
-
100,000 SF additional warehouse space
|
|
TransGlobal Park Warehouse
Kinston, North Carolina
-
40,000 sf warehouse
-
Standing Seam (SSR) Roof System
-
Structural tilt wall
-
Continuous beam primary framing
-
10,000 SF of office space |
|
Signature Flight Support Facility
Teterboro, New Jersey
-
(2) Twin 40,000 SF hangers
-
Standing Seam (SSR) Roof System
-
Panel Rib Walls
-
Rigid Frame (clear span) primary framing
-
10,000 SF of office space |
|
Gulfstream SWQ Phase I
Savannah, Georgia
-
Secondary system on conventional framing
-
Insulation and liner panel assembly
-
Span-Lock (concealed fastener) wall panels |
|
Interbake Foods
Front Royal, Virginia
-
185,000 SF Plant Expansion
-
90 x 90 Tower 70’ Tall
-
SSR with Widebay
-
Metlspan partition between tanks
-
20 Year Weather tightness Warranty
-
Completed in 4 months
|
|
NAVFAC - Engineering Operations Center
Naval Air Station Jacksonville, Florida
-
Structural Deck installation
-
Insulated wall panels
-
Tilt wall construction with conventional framing
-
2" SLR roof system
-
4" rigid insulation with underlayment
-
LEED Certified Silver |
|
Coca-Cola Bottling Co.
Harahan, LA
-
280,000 sf warehouse with 32' eave
-
52,000 sf 100' tall automated warehouse
-
Repairs from hurricane damage
-
remove damaged siding and roof system
-
reinstall new siding and roof system
-
Existing operations back working in 2 weeks
-
Project complete in 4 months
Ask Jason about disaster recovery and preperation
|
|
Moogs Manufacturing / Warehouse
Murphy, North Carolina
|
|